We poured in the early evening. It was the best time according to our schedules, but probably not the best time according to the sun. In the afternoon the sun hits full onto this side of the building and, between the bricks and the asphalt, it can get pretty hot. Add a layer of sunblock and it feels great, but the concrete sets up faster that way. It gets thick and goopy coming down the chute; the driver kept hosing it down to keep it moving easily.
This picture shows the wooden forms PC built against the building:
Remember those asphalt squares that were removed from the parking lot? PC was able to dig them out about 18 inches. The soil beneath the parking lot was packed very tightly and made for some hard digging. He found a few glass shards and some old bones. (Bones!? Yep. There's a story there, don't you think?)
Next, he built wooden forms around the boxes to bring them all up to the same elevation because the parking lot slopes slightly toward the street (I didn't get pictures of the tool he uses to do that - I was busy holding the measuring stick).
This isn't the greatest picture, but it'll give you an idea of what he did. The wood around the outside, obviously, is to form the concrete into shape and to bring it to the proper elevation. The 2x4 across the top is there to hold the 'J' bolts in place. (They're really shaped like the letter 'L' with a long vertical leg, but they're called 'J' bolts. I don't know why, I'm just telling it.) On top you can see those two little knobs - those are the threaded ends with washers and bolts and covered in duct tape to protect them from the concrete (it gets messy). The long ends are floating down in the hole so they're anchored good and tight once everything sets up. You can see the pencil marks on that 2x4, too. He's got it set up perfectly to bolt down the columns that will support the entryway overhang. (Right now the columns are sitting in the garage here at home waiting for me to wire-brush them, sand them and paint them. Instead, I'm sitting here drinking coffee and writing blog entries.)
Here's PC doing some last minute reinforcing. I'm sure that there's some formula for figuring out the amount of pressure that gets exerted against concrete forms, but I don't know what it is. It's enough for me to know that it's a LOT. TONS. Or more.
I've never seen forms blow out, probably because I've always helped pour into forms that PC builds and anything that PC builds will not be going anywhere anytime soon. Anytime soon meaning in the next hundred years or more (way more). (I'll have to show you pictures of the log cabin that he built -but that's way off topic....)
Apparently, though, blowing forms is not all that uncommon. PC has says when it happens they explode. Yikes.
Here it comes, pouring the boxes first, PC ready with the shovel:
A quick thank you to Curtis for helping out with this pour and also to Jim Mayle, the driver from Builder's Service & Supply. This isn't the first time that Jim has brought us concrete. He's delivered to our house at least a couple of times - once core filling the block walls for the garage and once for half of the floor in the garage (one of these days we'll do the other half). Jim is soft-spoken and patient and he knows what he's doing. Thank you, Jim.
Blogger wouldn't let me upload more than these 5 pictures so, instead of fighting to move them around I'll just start another post. I have time, I think; the kids were worn out last night....
Saturday, May 3, 2008
Outside - Pouring Concrete Part 1
Monday, April 21, 2008
Pitching In - Part 2
The 123 is the perfect size -and shape- for a small Coffee House. The layout is just about perfect. The main thing we weren't happy with was the front entrance. While the narrow Main Street face of the building with the single window and slight door were perfect for a small dentist's office, we felt we needed to open things up and create a welcoming entrance. If you've been following along you'll know that we intend to move the main entrance around to the west side facing the parking lot (see this post about brick cutting). And now that we have the inside well under way, it's time to start outside and get ready to open up the building.
One of the main things that needs to be done outside is to construct the gabled overhang that will protect the front entrance from the weather. There are several steps involved in this, but since we're talking about everyone pitching in to help, this post is about Screech and her contribution this past weekend.
See the squares that have been removed from the surface of the parking lot? These had to be removed to enable us to dig down until we hit bedrock. These will be the foundation points for the posts that will support the roof.
Here's Screech prying the last of the asphalt up:
See the yellow handled chisel right behind her? She used that and the hammer to chip a small corner out to give her a place to start to get in under the asphalt. . Then she used that pry bar (a pipe with a flattened end) in her hand to get in underneath and pry it up. When the whole square popped up, she stuffed one of those 2x4 pieces under it and then used a sledgehammer to whack until it cracked into pieces. She then pried up the pieces and set them into the wheelbarrow.
In this picture you can see the squares in relation to the building:
I'll get to what PC is doing in a later post. I do have a couple more pics I want to post that relate to the squares, but I have run to the end of my patience with formatting pics and text. I will have to start another post to add them....
Sunday, April 20, 2008
Pitching In - Part 1
I spent most of the afternoon at The 123. I decided I needed to put in a couple of hours of drywall *mudding, so I loaded up Screech and Dozer and headed down there to meet PC.
This Coffee House construction has really become a family project - everyone pitches in according to their ability. I figured that was good fodder for blog food so I went through some pictures....
Here are a couple of shots of one of the scrap recycled wood sculptures that Dozer built:
And here he is pounding away (note the safety glasses - required): This particular piece, I believe, was random. Once he finished with this, he went on to build a spaceship, at least one boat, and a race car.
*'Mudding' is not a word, at least not according to blogger or my word processing program. I know I'm not the only one who knows 'mud' can be a verb; drywall mudding is not the only type of mud activity for which it should be used as a verb, either.
Friday, February 1, 2008
Construction!
I'm always 2-3 weeks behind when it comes to posting pictures; these two pictures are from January 9th. I will take more pictures this weekend and again on Monday when the drywall is scheduled for delivery (yay!).
This first picture is just a shot of the saw horses and 2x4s.
This picture shows the beginning framing for the ceiling soffit. In the interest of keeping the high ceilings, we compromised with a soffit that will cover the duct work for the second floor and some of the other utility stuff. Some things will still be exposed, but we can make those things look good.